INTEGRATED PROJECT DELIVERY:
AN UPDATED
WORKING DEFINITION
VERSION 3 UPDATED 7/15/14
1 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
INTRODUCTION
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
THE AMERICAN INSTITUTE
OF ARCHITECTS,
CALIFORNIA COUNCIL
1303 J Street, Suite 200
Sacramento, CA 95814
916/448-9082
916/442-5346 fax
WEBSITE: www.ipd-ca.net
INTRODUCTION
This document,
Integrated Project Delivery: An Updated Working Definition
,
contains the recommendations of the AIA California Councils Definitions
Committee of the Integrated Project Delivery Task Force. Several years have
passed since the initial development of this document in 2006. While the
original document, on the surface, is surprisingly intact, there is recognition
that the document could benefit by refreshing the definiton and principles
based on implementation of actual Integrated Project Delivery projects. To
date, we are aware of over 200 projects that use multi-party contracts to
incentivize and reward their teams in project execution, with likely 100s or
even 1,000s that use the principles of Integrated Project Delivery to improve
project outcomes.
It is largely this proliferation of projects using IPD principles that has
prompted this Updated Working Definition. Projects using incomplete models
of integration, often called “IPD-ish,” have caused much confusion in the
industry. This document proposes drawing a line in the sand as to what is IPD
and what is not IPD. This document identifies what IPD is; either a project is
providing all the ingredients and it is IPD or it is not.
The organization of the
Updated Working Definition
is similar to that of the
original document, with the addition of a section containing a comparison
between Integrated Project Delivery and more traditional delivery models. This
document also amends the text with real world experiences from the use of
Building Information Modeling, large collaborative project spaces, aka “the big
room” and implementation of risk sharing/incentive rewards on projects that
have gone well.
The Task Force will continue to use the
Updated Working Definition
as the
basis for developing recommendations for best practices, integrated project
delivery models, and risk allocation. Why is the document still a “Working
Definition?” Integrated Project Delivery is still in its infancy.
When this delivery model is being used more commonly, there will be
sufficient data to clearly define the boundaries of Integrated Project Delivery.
Until then, the group invites you to comment on the
Updated Working
Definition
, by writing to [email protected]g.
“Projects using incomplete
models of integration,
often called “IPD-ish,” have
caused much confusion in
the industry. This document
proposes drawing a line in
the sand as to what is IPD
and what is not IPD.”
3 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
TABLE OF CONTENTS
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
CONCEPTUAL-
IZATION
CRITERIA
DESIGN
DETAILED
DESIGN
IMPLEMENTION
DOCUMENTS
CLOSEOUTAGENCY
COORD/FINAL
BUYOUT
CONSTRUCTION
HOW
WHO
REALIZE
WHAT
PAGE 8 PAGE 8 PAGE 9 PAGE 9 PAGE 10 PAGE 10 PAGE 10
IPD DEFINITION
PAGE 4
THE VALUE PROPOSITION
PAGE 5
ESSENTIAL PRINCIPLES
PAGE 6
PHASES
PAGE 7
OPTIMIZED IPD
PAGE 11
GLOSSARY
PAGE 16
CONCLUSION
PAGE 15
IN COMPARISON WITH OTHER DELIVERY MODELS
PAGE 13
ACKNOWLEDGEMENTS
PAGE 17
TABLE OF CONTENTS
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
4 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
TABLE OF CONTENTS
TABLE OF CONTENTS
IPD—THE DEFINITION:
Integrated Project Delivery (IPD) is a project delivery method that integrates people, systems, busi-
ness structures and practices into a process that collaboratively harnesses the talents and insights of
all participants to reduce waste and optimize efficiency through all phases of design, fabrication and
construction. The Integrated Project Delivery method contains, at a minimum, all of the following elements:
Continuous involvement of owner and key designers and builders from early design through project
completion
Business interests aligned through shared risk/reward, including financial gain at risk that is de-
pendent upon project outcomes
Joint project control by owner and key designers and builders
A multi-party agreement or equal interlocking agreements
Limited liability among owner and key designers and builders
IPD requirements, as a project delivery model, are noted above. Projects using
components of IPD, not in its entirety, are not IPD. This document’s goal is to state that
projects wanting to use IPD must incorporate all aspects of the definition for it to be
considered IPD.
Note: Integrated Project Delivery teams will usually include members well beyond the ba-
sic triad of owner, designer and contractor. At a minimum, though, an integrated project
includes tight collaboration between the owner, architect/engineers, and builders ultimately
responsible for construction of the project, from early design through project handover.
Many of the essential elements of Integrated Project Delivery may be applied to a variety
of collaborative project delivery methods, such as Design-Build or CM at Risk, that may
not inherently contain every required IPD element mentioned above.
FURTHER EXPLANATION:
Integrated Project Delivery (IPD) is a project delivery method: IPD is
a unique and separate project method, distinctly different from Design-Bid-Build,
Design-Build, CM at Risk, and Multiple Prime. All benefits for innovation and efficiency
return to the project team as opposed to the individual firms. All parties agree to the
business terms to share the financial savings for optimizing the Owner’s business case.
Integrates people, systems, business structures and practices: The
foundation for IPD is the development of a virtual project organization. The organization
of “the firms” includes the individual team members for the owner, designer(s),
consultants and builder(s). The project organization’s mission and responsibilities are
committed to “best for project” decision making, and this commitment is supported by
alignment of the firms’ business interests through shared risk and reward.
Collaboratively harnesses the talents and insights of all participants:
The primary purpose of the virtual organization is collaboration. The project firms and
individuals are committed to create a team culture of joint decision-making. Team
members are formally organized in multidisciplinary clusters responsive to the project
goals. Team members are individually accountable to contribute alternatives to design
and construction issues. Builders’ input is not left until the construction phase, when it
is typically too late to benefit the design.
Reduce waste and optimize efficiency: IPD incentivizes minimization of
waste. In addition to integration and collaboration, the method utilizes formal tools to
achieve maximum results. Typical tools include: Building Information Modeling (BIM),
prefabrication, manufacturing of larger integrated units, process improvement metrics and
LEAN design and construction techniques.
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
5 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
IPD—THE VALUE PROPOSITION
IPD—THE VALUE PROPOSITION
IPD—THE VALUE PROPOSITION:
The owner’s “business case” defines the need for and the requirements of a capital
project. The ultimate goal for an owner is to complete a project to meet very specific
business goals within very specific constraints. Typically these constraints, at
the highest level, are budget, schedule and a level of quality required to support
operations, all within a predicable level of risk. Generally speaking, the industry
suggests that the owner can expect to optimize any two of the three constraints but
not all three; Integrated Project Delivery enables optimizing all three.
Previously, there were four main project delivery models available to owners:
Design-Bid-Build, Design-Build, CM at Risk, and Multiple Prime. Each offers a
different level of predictability to project outcome and risk.
Integrated Project Delivery (IPD) is a fifth delivery model that is gaining momentum.
IPD offers owners the maximum opportunity to optimize their business case within
predicable risks.
WHAT IS THE VALUE PROPOSITION FOR IPD?
1. Flexibility: Consider for example, that a business case
includes additional goals and constraints such as:
aesthetics, sustainability, operating efficiency, life cycle
costs, community relationships, local workforce, and
numerous others specific to an owner’s project. Often
not considered, however, is the need for flexibility to
accommodate change during design or construction
without sacrificing the owner’s constraints! Projects
are becoming more complex; technology, equipment,
innovations in products, manufacturing, and prefabrication
are becoming available faster than projects can be
completed. The owner may require late incorporation to
stay competitive or respond to an unanticipated change
in their business environment. IPD’s shared financial
incentives between owner, designer(s) and builders(s) and
integrated and collaborative processes enable the team to
collectively find the project solution to optimize and support
the business case.
2. Speed: After an initial investment in learning how an
integrated team works, The information flow on IPD
projects moves more quickly for the following reasons:
First, designers and builders coordinate directly during
design, thus preventing the misunderstandings and poorly
informed design decisions that typically create delays
during construction. Secondly, by fostering an environment
in which the team collaborates well, questions get
answered in the speed of a conversation instead of a paper
trail that starts with an RFI and ends with a change order,
typically taking weeks to process.
3. Less litigation: At the date of publication, no IPD project
has gone into litigation. This is because IPD projects create
a structure wherein all core team members benefit or suffer
together, incentivizing them to help each other prevent
problems. Disputes that typically would lead to claims are
either prevented or settled in a collaborative manner.
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
6 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
IPD—ESSENTIAL PRINCIPLES
IPD—ESSENTIAL PRINCIPLES
WHICH ARE
FOSTERED
OUT OF
THESE
BY THESE
WHICH ARISE
OPTIMIZE
THE
WHOLE
IPD—ESSENTIAL PRINCIPLES:
1 Optimize the Whole, not the parts: The point of integrating
the project team is to deliver the whole project in a way that
gives owners what they value. Whether that is optimized
design solutions, increased efficiency over the building’s
lifetime, or a fast track schedule, higher performance
requires that all parties make decisions that are best for
the project, rather than their own slices of the pie.
2 Early and Clear Goal Definition: In order to optimize
the whole, the team must agree on what the “whole” is.
Project goals are developed early and agreed upon by
all participants. Project budget is set early and the team
designs to the price, rather than pricing a design.
3 Collaboration: In order to optimize the whole, the project
team must collaborate closely, deeply, and continuously.
4 Integration (people and systems): People can’t collaborate
unless they can easily share information, find appropriate
times and spaces to communicate, understand how
their different design processes interact, get their billing
departments to work in harmony, and get many other
systems (big and small) integrated together across
company lines.
5 Joint Ownership: Meaningful collaboration requires
participants to have a sense of ownership over the project
and end goals.
6 Respect: Collaboration also requires respect. The project
team mutually commits to treating each other with
respect and valuing each professionals input. Innovative
solutions can come from any team member, so roles are
not as strictly defined as on traditional projects, but rather
assigned to the best qualified person.
7 Trust: Meaningful collaboration cannot occur without trust.
Trust is fostered through experience together, as well as
purposeful decisions.
8 Transparency: Trust requires transparency.
Communication among the team is not limited to
traditional silos or top-down distribution. Information of
all types, from design rationale to Building Information
Modeling (BIM) lives in a central location so all team
members have access to accurate and current information.
Often an investment in technology compatibility will be
necessary to ensure that all team members have access to
the information they need to coordinate.
9 Safe Environment: Trust also requires a project
environment in which team members are safe to
experiment and suggest innovations without fear of
being wrong.
10 Shared Risk and Reward: An integrated project depends
on best-for-project decision-making. However, it is very
rare that a firm will actually sacrifice its own profitability
for the good of a project. Under IPD, risk/reward sharing
structures are set up to cost or benefit the participants
according to
project
outcomes rather than
individual firm
contributions. This aligns the decision-making influences
– a decision that is best for the project will benefit all
participants, one that attempts to benefit one firm at the
expense of the project will reduce profitability for all
participants.
11 Good Technology: Integrating systems together across
company lines becomes much easier when using good
technology. For projects requiring high levels of integration,
technology like Building Information Modeling (BIM),
cloud servers, teleconference tools, and others become
crucial to making it all work. It is important to factor in the
investments in both money and time to get these up and
running smoothly.
THE
WHOLE
POINT
COLLABORATION
RESPECT
JOINT
OWNERSHIP
INTEGRATIONTRUST
TRANSPARENCY
SAFE
ENVIRONMENT
SHARE RISK
& REWARD
GOOD
TECHNOLOGY
EARLY & CLEAR VALUE
DEFINITION
YOU NEED
THESE
TO GET THIS
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
7 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
IPD—PHASES
PRE-
DESIGN
CONCEPTUAL-
IZATION
SCHEMATIC
DESIGN
CRITERIA
DESIGN
DESIGN
DEVELOPMENT
DETAILED
DESIGN
CONSTRUCTION
DOCUMENTS
IMPLEMENTION
DOCUMENTS
BUILDERS
BUILDERS
CLOSEOUT
CLOSEOUT
AGENCY
PERMIT/
BIDDING
AGENCY
COORD/FINAL
BUYOUT
CONSTRUCTION
CONSTRUCTION
HOW
HOW
WHO
WHO
REALIZE
REALIZE
WHAT
WHAT
INTEGRATED
DESIGN PROCESS
TRADITIONAL DESIGN
PROCESS
IPD—PHASES:
Who: The project participants
What: The physical and functional requirements of the
project
How: The means and methods that will be used to make
the “What” real
Realize: The act of making the “What” real – i.e. construction
The phases of an Integrated Project differ from traditional
phases (Schematic Design, Design Development, Construction
Documents, etc.) in order to take advantage of two critical
factors:
In addition to the design expertise of a traditional design
team, expertise in construction aspects (cost, scheduling,
material performance and availability, means and meth-
ods, etc.) is available throughout the design process.
Building Information Modeling (BIM) tools and processes
enable the team to integrate this broader range of knowledge in
order to provide effective support for design decisions.
These factors enable the team to make better-informed design
decisions earlier in the process and to optimize the design
for construction means and methods. In essence,
how
and
who
are addressed much earlier in the process, enabling
elimination of the traditional overlap of
what
and
how
with
realization
that is typically a source of expensive changes and
rework during construction.
This is not to suggest that there is a rigid, sequential order
to phasing in an integrated project. The expanded knowledge
base and enhanced collaboration tools in an integrated team
allow a great deal of flexibility in the sequencing of the design
effort. A major advantage of the integrated approach is that
the team makes the decisions regarding this sequencing.
In traditional projects design decisions are often deferred -
sometimes even until after start of construction - at the sole
discretion of the designers, without complete knowledge of the
impact on construction. In an integrated project, however, the
availability of both design and construction expertise enables the
team to sequence the design effort to better accommodate such
issues as fast-track delivery or procurement of long-lead items.
TRADE BUILDERS
TRADE BUILDERS
OWNERS
OWNERS
DESIGNER
DESIGNER
DESIGNER CONSULTANTS
DESIGNER CONSULTANTS
AGENCY
AGENCY
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
8 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
IPD—PHASES
IPD—PHASES
SETTING THE STAGE
Prior to actual kickoff of the design process,
or concurrent with the very earliest steps,
significant preparatory work will need to be
done.
Key project participants are selected and brought on
board. The actual personnel should be brought in.
Owner
Prime Designer
Key Design Consultants
Prime Builder
Key Trade Builders
Key Regulatory Agencies
Team communication/coordination processes are set up.
Collaboration training
Communication technologies
The business model for the project is determined
The risk/reward structure that will best incentivize the
accomplishment of the Owner’s goals for the project is
developed
IPD contract(s) is (are) negotiated
Project management structure is set up
Key technologies are identified and protocols are set up
for their use. Examples:
Building Information Modeling
Change control protocols
Model management responsibilities
Performance simulation tools
Document Management System
Data exchange protocols
Extent of co-location is determined, and co-location
facility is designed and set up
1 CONCEPTUALIZATION
Conceptualization begins to determine WHAT is
to be built.
All key stakeholders are involved in the programming
process; input is obtained from as many participants as
possible.
Key project parameters are captured, such as:
Size
Schedule
Sustainable or green criteria or goals
Performance metrics (economic, energy, maintenance
efficiency, operational, etc.)
Initial cost structure is developed. Benchmarks by which
cost targets for the project will be determined are identified.
Preliminary schedule is developed.
2 CRITERIA DESIGN
During Criteria Design the project is defined and
the targets and metrics by which the success of
the project will be measured are agreed upon.
Key project parameters such as the following are fixed:
Scope
Basic design (massing, elevations, floor plans, etc.)
System selection (structural, skin, HVAC, etc.)
Quality levels for finishes
Target Cost
Overall schedule
Building components to be prefabricated
Sustainability targets
All key trade contractors are engaged.
Procurement schedule is developed.
Cost structure is refined to a system level, in a manner
that enables the team to use the cost information to guide
the design.
CONCEPTUAL-
IZATION
CRITERIA
DESIGN
DETAILED
DESIGN
IMPLEMENTION
DOCUMENTS
CONSTRUCTORS
CLOSEOUTAGENCY
COORD/FINAL
BUYOUT
CONSTRUCTION
HOW
WHO
REALIZE
WHAT
INTEGRATED
DESIGN PROCESS
TRADE BUILDERS
OWNERS
DESIGNER
DESIGNER BUILDERS
AGENCY
CONCEPTUAL-
IZATION
CRITERIA
DESIGN
DETAILED
DESIGN
IMPLEMENTION
DOCUMENTS
BUILDERS
CLOSEOUTAGENCY
COORD/FINAL
BUYOUT
CONSTRUCTION
HOW
WHO
REALIZE
WHAT
INTEGRATED
DESIGN PROCESS
TRADE BUILDERS
OWNERS
DESIGNER
DESIGNER CONSULTANTS
AGENCY
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
9 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
IPD—PHASES
IPD—PHASES
3 DETAILED DESIGN
The Detailed Design phase concludes the WHAT
phase of the project. Note that the Detailed
Design phase is longer and more intense than
traditional Design Development because more
is accomplished. The team will decide the level
of detail required.
During this phase, all design decisions
necessary to ensure that changes during
construction will not be necessary are finalized,
and the design is fully and unambiguously
defined.
All building elements are defined.
All building systems are fully engineered and
coordinated. This includes final system coordination that
in traditional delivery models is usually deferred until the
construction phase because trade contractor input is not
available until then.
Specifications are developed based on agreed and
prescribed systems.
4 IMPLEMENTATION DOCUMENTS
During this phase, focus shifts from WHAT is
being created to documenting HOW it will be
implemented. At the beginning of this phase
the entire building and all systems are fully
defined and coordinated, so it is significantly
shorter than the traditional Construction
Documents phase.
The traditional shop drawing process is merged into the
design as the contractor, trade contractors, and suppliers
document the construction intent of building systems and
components.
Prefabrication of some systems can commence because
the design is fixed.
Specifications are developed to provide narrative
documentation of the design intent wherever necessary.
Documents are generated where needed for processes
such as:
Financing
Procurement
Permitting
Implementation Documents include information for
Assembly
Layout
Detailed schedule
Procedural information (testing, commissioning)
Legal requirements (whatever needs to be included to
be legally binding)
5 AGENCY REVIEW
This phase actually runs concurrently
with Criteria Design, Detailed Design, and
Implementation Documents. During the earlier
phases the regulatory agencies provide
high-level compliance information and work
with the team to develop a mutually agreeable
permit submittal schedule. Because of their
involvement in the design process, builders
and trade builders will need to be involved in
submittal preparation and response to
agency comments.
CONCEPTUAL-
IZATION
CRITERIA
DESIGN
DETAILED
DESIGN
IMPLEMENTION
DOCUMENTS
BUILDERS
CLOSEOUTAGENCY
COORD/FINAL
BUYOUT
CONSTRUCTION
HOW
WHO
REALIZE
WHAT
INTEGRATED
DESIGN PROCESS
TRADE BUILDERS
OWNERS
DESIGNER
DESIGNER CONSULTANTS
AGENCY
CONCEPTUAL-
IZATION
CRITERIA
DESIGN
DETAILED
DESIGN
IMPLEMENTION
DOCUMENTS
BUILDERS
CLOSEOUTAGENCY
COORD/FINAL
BUYOUT
CONSTRUCTION
HOW
WHO
REALIZE
WHAT
INTEGRATED
DESIGN PROCESS
TRADE BUILDERS
OWNERS
DESIGNER
DESIGNER CONSULTANTS
AGENCY
CONCEPTUAL-
IZATION
CRITERIA
DESIGN
DETAILED
DESIGN
IMPLEMENTION
DOCUMENTS
BUILDERS
CLOSEOUTAGENCY
COORD/FINAL
BUYOUT
CONSTRUCTION
HOW
WHO
REALIZE
WHAT
INTEGRATED
DESIGN PROCESS
TRADE BUILDERS
OWNERS
DESIGNER
DESIGNER CONSULTANTS
AGENCY
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
10 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
IPD—PHASES
IPD—PHASES
7 CONSTRUCTION
In traditional projects construction is often
treated as the final stage of design where
issues that were not addressed during the
design phases are worked out. In an Integrated
Project, due to the availability of construction
expertise as well as the ability to integrate
this expertise into the design using BIM, final
design is completed during Detailed Design
and means and methods are worked out during
Implementation Documents.
Some elements of IPD construction
administration will remain similar to traditional
practice. For example:
Quality control, inspection and testing will be relatively
unchanged.
Change orders, particularly for owner directed changes,
must be formally negotiated and documented.
Scheduling and progress will be periodically reviewed.
CONCEPTUAL-
IZATION
CRITERIA
DESIGN
DETAILED
DESIGN
IMPLEMENTION
DOCUMENTS
BUILDERS
CLOSEOUTAGENCY
COORD/FINAL
BUYOUT
CONSTRUCTION
HOW
WHO
REALIZE
WHAT
INTEGRATED
DESIGN PROCESS
TRADE BUILDERS
OWNERS
DESIGNER
DESIGNER CONSULTANTS
AGENCY
8 CLOSEOUT
Many aspects of the closeout of an Integrated
Project will be similar to those of traditional
projects. Some examples:
Finalization of as-built models or other documentation
Punch list correction
Warranty obligations
Occupancy and completion notification
In addition, the painshare/gainshare arrange-
ment will be resolved.
6 BUYOUT
The bulk of an IPD project is not “bought out” as
in traditional projects because the major trades
develop their prices during the design process.
In addition, long-lead items are identified and
defined during design and their procurement is
begun as early as necessary. This Buyout phase
completes the buyout of remaining contracts.
CRITERIA
DESIGN
DETAILED
DESIGN
IMPLEMENTION
DOCUMENTS
BUILDERS
CLOSEOUTAGENCY
COORD/FINAL
BUYOUT
CONSTRUCTION
HOW
WHO
REALIZE
WHAT
INTEGRATED
DESIGN PROCESS
TRADE BUILDERS
OWNERS
DESIGNER
DESIGNER CONSULTANTS
AGENCY
CRITERIA
DESIGN
DETAILED
DESIGN
IMPLEMENTION
DOCUMENTS
BUILDERS
CLOSEOUTAGENCY
COORD/FINAL
BUYOUT
CONSTRUCTION
HOW
WHO
REALIZE
WHAT
INTEGRATED
DESIGN PROCESS
TRADE BUILDERS
OWNERS
DESIGNER
DESIGNER CONSULTANTS
AGENCY
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
11 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
OPTIMIZED SUMMARY
OPTIMIZED SUMMARY
BUSINESS MODEL
Separate Profit from Cost
Establish a fixed profit. Separating profit from units of labor
or materials eliminates the incentive to increase the number
of units to increase profitability. Instead, the incentive should
be to increase margin by reducing the underlying costs while
maintaining a fixed profit amount. Ideally, 100% of a parties
profit should be at risk. Moreover, the at-risk profit provides
the owner with a buffer against cost overruns, and less than
full profit at risk can result in an inadequate buffer.
Guaranteeing Costs To Perform The Work
There are several reasons for the owner guaranteeing costs
without a cap. First, whenever a cap is placed on costs, the
capped party wisely includes contingencies in its costs to
protect against the potential cost overrun. Second, if there
are any project disruptions, the parties will begin the claims/
change order process to avoid losing claim rights that may be
important if the project continues to suffer additional costs.
This creates an antagonistic project atmosphere—often from
early in the project. Finally, the variable cost guarantee is a fair
trade for the fixed profit being at risk and the limits on change
orders.
Profit Based on Agreed Project Outcomes
Tying profit to achieving agreed project outcomes assures
goal alignment and increases the likelihood of aligned action.
The agreed outcomes can be whatever is most important to
the owner and the team. Often this will be cost and schedule,
but can also be quality, sustainability, functionality, life cycle
costs, owner satisfaction or whatever else the team may agree
upon. By tying profit to project, instead of individual outcomes,
the team is incentivized to collaborate in pursuit of common
objectives and disincentives selfish behavior.
Limited Entitlement for Change Orders
Increasing project costs by change orders is limited to
owner elected changes. Team caused impacts, such as
errors and omissions in the drawings, construction errors
or productivity issues are issues for the team to resolve,
not opportunities for additional revenue. This attribute, in
conjunction with limited liability and profit based on project
outcome, creates a closed system. If problems arise, the
team must collaboratively resolve them regardless of cause.
Entitlement for change orders and claims is largely eliminated
in IPD. Once understood, this attribute leads to more effective
constructability evaluations, coordination and response to
problems as they occur.
CONTRACT STRUCTURE
Early Involvement of Key Participants
The key parties are contractually engaged at the earliest
responsible moment. Key parties are those that have a
substantial stake or material effect on project outcome.
Involving these parties early has many beneficial effects.
First, it increases the overall knowledge base before design
is developed, allowing for coordination and constructability
to be built into the process rather than applied after the
fact, enabling target value design, and eliminating value
engineering. This improves the designer’s understanding
of systems, equipment, alternatives and costs implications
before they initiate design. It also increases the diversity of
opinions and perspectives—a key determinant of creativity.
It avoids much of the rework inherent in the transfer of
design information to builders and can allow for an efficient
distribution of design effort between the licensed design
professionals and the design/assist or design/build trades.
Joint Project Control & Decision Making
Joint project decision making is an essential step in creating a
virtual organization. By empowering the team to jointly manage
the project, decision making is accelerated and situated closer
to the sources of knowledge and information. Because major
decisions are not unilateral, there is a check-and-balance
that reduces the likelihood of errant decisions. Joint project
decision making also increases overall ownership of the
project, leading to higher levels of commitment. It is also fair.
Parties that have placed their profit at risk should have a voice
in project management.
Shared/Risk Reward Based on Project Outcomes
This is the contractual tie between profit based on agreed
outcome and limitations on change orders. By putting both of
these attributes in an enforceable agreement, the business
model becomes an obligation, not an aspiration. This is one
OPTIMIZED IPD
The elements of IPD listed on page 4 are at IPD’s core. Below is a discussion of the
key constructs that enable an optimized IPD project. These constructs comprise the
optimal business model, contractual structures and team behaviors. Also included
is the critical discussion as to how each construct contributes to enabling an IPD
team to be more successful than other delivery models. These constructs are
characteristics that are specific to those members directly signatory to a single or
multiple interlocking IPD agreement(s).
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
12 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
OPTIMIZED SUMMARY
OPTIMIZED SUMMARY
of the distinctions between true IPD and other collaborative
approaches, such as partnering, that seek to achieve
behavioral changes—but these can be abandoned mid-project
because they are not a contractual obligation.
Jointly Developed Validated Targets/Goals
The jointly developed and validated targets/goals are an
enforceable “mission statement” for the project. Because they
are used to determine project success—and compensation—
they align the team’s actions to the agreed goals. Agreement to
goals also leads to commitment to achieving them. In addition,
they provide a check, through the validation process, on the
feasibility of the project. Aggressive goals also create the
stress that leads to behavioral change, but because the stress
is felt by all project members, it becomes a shared incentive to
jointly develop new and more effective approaches.
Reduced Liability Among Risk/Reward Members
Reduced liability is an element in closing the system, forcing
the participants to take responsibility for the project rather
than attempting to blame other participants in an attempt
to escape the impact of a problem. But perhaps more
importantly, it removes disincentives to direct and continuous
communication between the parties. Because parties who
suffer because of incorrect information can often claim against
the information provider, project participants (particularly
the design professionals) have become wary of providing
early and incomplete information to contractors. But without
an understanding of where the designers are headed, the
builders cannot effectively plan. Similarly, builders are chary
of providing advice about design that might draw them into a
design issue. But if the team is to be effective, communication
must be rapid, direct, and continuous. Reducing liability among
risk/reward team members removes much of the anxiety
around communication.
ENABLING BEHAVIORS
Optimize the Whole, Not the Parts
Essential change in IPD is that the project is viewed as an
indivisible whole. Every action, every decision should be
judged by whether it will lead to improving the overall project
outcome. This is the critical difference from other project
delivery methods as compared to IPD. All participants,
including the owner, designers and builders, in an IPD
arrangement work together to optimize the project result
rather than benefit the individual firms.
Trust
Trust is a critical element of IPD. But it is not blind trust.
It is trust built on transparency and respect and measured
accountability to meet commitments. When trust is created,
the entire project is accelerated. The parties can trust their
colleagues to perform as they promised allowing everyone
to plan based on those promises. Moreover, the parties can
trust that their colleagues will respect their interests and
ideas, creating a safe environment to extend their capabilities.
Earned trust catalyzes every transaction between the parties.
This kind of trust is seen with firms that have proven track
records, renown reputations or past experiences working on
previous projects before with other team members.
Integration (information, people and systems)
High performance projects and project delivery requires
integration throughout the process. Integrated information
provides a means for information exchange and developing a
common understanding. Integrated organization melds the
disparate companies and individuals into a virtual organization.
Integrated processes lead to coordinated and efficient action.
Integrated systems enable optimization of the entire project.
Integration creates the possibility of utilizing the capabilities of
the entire team and creating results that are greater than the
sum of the parts.
Continuous Improvement/Learning
IPD is not a static concept. It is a process of continual
examination and improvement. In IPD, learning is not just
the subject of retrospectives. It is a daily process where
learning is turned into action, tested, modified, tested again,
throughout the project. Processes are studied and challenged,
experiments undertaken, and the results immediately fed back
into the project. The goal of IPD is is to deliver this project
better than originally envisioned.
Appropriate Technology
IPD does not demand any specific technology and technology
should not be seen as a crutch for failed procedures. Systems
and procedures should be optimized before being automated.
But most IPD projects will rely on appropriate technologies,
particularly Building Information Modeling. BIM is an
important vehicle for collaboration. It is a platform for rapid
prototyping and simulation, creates a common understanding
between the parties and is a tool for identifying and resolving
conflicts. Astute IPD teams take advantage of project websites,
simulation and optimization software, 3, 4 and 5D models, and
any appropriate tool that will increase understanding, promote
communication, collaborate virtually, and better achieve
the project objectives. Thus, while no specific technology
is required, not using technology appropriately violates the
principles of continuous improvement and optimizing
the whole.
Collaboration
IPD requires collaboration, not just cooperation. Collaboration
is working together to achieve the agreed goals by building on
and improving each others’ ideas. It is synergistic and creates
results that exceed what can be achieved by coordination,
alone. Collaboration in IPD is most visibly shown through
co-located activity, where the parties are not just meeting
together, they are performing their daily work together
in cross-functional groups composed of the best suited
individuals drawn from all of the IPD participating firms. They
engage in a vigorous exchange of ideas and perspectives
to develop solutions to project problems and to achieve the
common goals. Peter Senge and others referred to this
exchange as dialogue. It is not an exchange seeking to win a
debate, but a joint exploration leading to solutions.
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
13 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
IPD—IN COMPARISON WITH OTHER DELIVERY MODELS
IPD—IN COMPARISON WITH OTHER DELIVERY MODELS
IPD—IN COMPARISON WITH OTHER
DELIVERY MODELS
IPD allow for a dynamic, transparent and holistic process that benefits all project participants.
These charts represent qualitative assessments of how IPD can be differentiated from other
delivery models. The delivery models show traditional delivery methods, but do not take into
account various contract models such as Guaranteed Maximum Price (GMP). The delivery
models chosen are comparators to IPD; Design Bid Build, Multi-Prime, Construction Manager
at Risk (CM at Risk) and Design Build represent the predominant delivery models used in
the industry. We did not include Turnkey or Public Private Partnerships as they embrace one
of the four models to deliver the design and construction of the building within the umbrella
of the longer contract for the building operation. The charts were developed from the broad
experience of the IPD Steering Committee members and contributors and do not represent
any research or collected field data from any specific projects. The overarching message, we
believe, will not change with any significant research, in that the only delivery model where
all the project stakeholders can benefit in all the studies is Integrated Project Delivery, and
sometimes Design Build.
CHART 1: Who benefits if the costs comes in lower or the schedule shorter depending on delivery
model type?
Owner Designer Builder Trade
Design Bid Build No No Yes Yes
Multi-Prime (hard bid) No No Yes Yes
CM at Risk No No Yes Yes
Design Build No Yes Yes Yes
IPD Yes Yes Yes Yes
CHART 2: Who is incentivized to keep the cost down or reduce the schedule for the owner when
changes occur?
Owner Designer Builder Trade
Design Bid Build Yes No No No
Multi-Prime (hard bid) Yes No No No
CM at Risk Yes No No No
Design Build Yes No No No
IPD Yes Yes Yes Yes
In chart one; one might not understand why the owner does not benefit with the costs coming
in lower than initially contracted. Traditional contracts do not require the sharing of savings on a
project with the owner. Project stakeholders are incentivized to reduce costs for their own benefit,
yet the owner does not always receive this benefit if the contract is not transparent and does not
share these outcomes.
Chart two shows that under traditional methods the owner is incentivized to keep costs
reduced as project requirements change, but the other project stakeholders are not.
This characterization of change is true for both owner generated changes, un-foreseen
conditions and errors / omissions. Under IPD, though, the team is incentivized to keep costs
down on a project when changes occur because the team is all being supplied from the
same source that will reward them. The transparent and single pool of monies in an IPD
model enables ownership from all project stakeholders for project success.
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
14 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
IPD—IN COMPARISON WITH OTHER DELIVERY MODELS
IPD—IN COMPARISON WITH OTHER DELIVERY MODELS
CHART 3: Who is incentivized to improve construction processes?
Owner Designer Builder Trade
Design Bid Build Yes No No No
Multi-Prime (hard bid) Yes No No No
CM at Risk Yes No Yes Yes
Design Build Yes Yes Yes Yes
IPD Yes Yes Yes Yes
Chart three begins to identify who wants to improve the quality and methodology of how the
project is delivered. Our industry is in a transition to embrace more advanced methods of
making buildings, as other manufacturing fields have. IPD, and sometimes Design-Build,
offer all the project team stakeholders the benefit when advanced delivery methodologies are
coordinated with others and the impact might not be cost neutral.
CHART 4: Who is incentivized to improve building performance for the lifecycle
Owner Designer Builder Trade
Design Bid Build Yes No No No
Multi-Prime (hard bid) Yes No No No
CM at Risk Yes No No No
Design Build Yes No No No
IPD Yes Yes Yes Yes
Chart four aligns project delivery with building performance. We think the main message is
that only through dynamic, transparent and holistic process benefiting all project participants
will our industry be incentivized to move the needle on how buildings perform. Building
system technologies and the actual functional requirements are constantly changing.
Traditional contracts are set up where the requirements and functionality are fixed. In
addition, design fees are also considered to be part of first cost competitive analysis by owners
and do not allow for lifecycle design. Since the lifecycle of a building is a significant portion of
the building’s cost for the initial capital outlay, our industry needs to provide a methodology
where the project delivery can support the eventual operations of the building.
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
15 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
CONCLUSION
CONCLUSION
CONCLUSION
This document refreshes and hones what IPD is. Specifically, it requires that for a project to
call itself an IPD model it must embody the minimum characteristics previously stipulated on
on page 4 for all key participants:
• Continuous involvement throughout the project
• Aligned business interest
• Joint project control
• Interlocking agreements or Multi Party Agreements
• Limited liability
We believe this is a necessary clarification to distinguish IPD from other delivery models
that offer some of these improvements, but do not use the whole system to achieve full
integration.
As stated in the introduction, this is a working definition, and in the future, we might find
reason to further define, or broaden the requirements of what stipulates an IPD model. The
goal of this document is to be a reference for industry practitioners who want to optimize their
projects and have their entire project team participate with them in concert, as opposed to
other delivery models that have silos where services and work are traditionally provided. We
welcome feedback and hope you can contribute to: ipd@aiacc.org
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
16 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
GLOSSARY
GLOSSARY
A GLOSSARY OF TERMS ASSOCIATED WITH IPD
Best-for-Project
Describes a decision making standard where decisions are
measured against shared goals / objectives about what is best
for the project vs. individual stakeholder outcomes.
Big Room
A shared space which includes at a minimum; the owner, the
design team and the constructor to encourage collaboration
and communication between all parties.
Building Information Model
A Building Information Model, (BIM) is a digital representation
of physical and functional characteristics of a facility.
Source: National Building Information Model Standard (NBIMS)
committee. For a more complete definition, see: http://www.
wbdg.org/pdfs/NBIMSv1_p1.pdf
Buyout
Buyout is the process of obtaining price commitments for all
work packages in a project. There are several methods by
which this can be accomplished, ranging from sealed bids
to direct negotiations. In the IPD approach most of the price
commitments are developed through a continuous effort, with
many of the trade contractors and suppliers participating in
the design and refining their prices as the project progresses.
Builder
Builder refers to the General Contractor who is responsible for
the project by providing all of the material, labor, equipment
and services necessary for the construction of the project.
Builder is also sometimes used to refer to trade contractors.
CM at Risk (Construction Manager at Risk)
Construction Manager at Risk (CM at Risk) is a project delivery
method that allows the client to select the Construction
Manager (CM) before the design stage is complete. The CM is
chosen based on qualifications, and then the entire operation
is centralized under a single contract. The architect and CM
work together in order to cultivate and assay the design.
Cost Model
A breakdown of the construction and project budget into
detailed “cost targets.” The cost targets are developed
collaboratively by the integrated team prior to commencing the
conceptualization phase of the project process. The structure
provides the benchmark for the team to support continuous
cost management as the project progresses to ensure that it
will be completed within the targeted budget.
Designer
The design professional on the project responsible for
performing and overseeing overall project design. Designer is
also sometimes used to refer to design consultants.
Design Consultant
The professional consultant(s) on the project responsible for
performing and overseeing design in specific areas of the work
(i.e., structural, mechanical, landscape, electrical, civil, etc.)
Integration
The coming together of primary participants (which could
include owner, designer, constructor, design consultants, and
trade contractors, key systems suppliers, etc,) at the beginning
of a project, for the purpose of designing and constructing the
project together as a team.
Interlocking Agreements
Agreement(s) used in an IPD project between the owner and
key designers and builders establishing shared risk/reward,
joint project control and limited liability.
Multi-party Contracts
Bind all the parties — client/owner, designers, constructor and
trade partners — into a single agreement which requires them
to share risks and rewards. This encourages everyone in the
team to think of the project first as their commercial interests
are clearly bound up with the overall success of the project. In
turn this means that leadership and decision making is both
more inclusive and distributed.
Multi-Prime
A method of contracting for construction wherein an owner
contracts directly with several (usually major) trades under
separate contracts to perform their work either simultaneously
or sequentially without employing a General Contractor to
be in overall charge of the work. The owner may provide the
management of the project, or hire a construction manager
to provide construction administration, coordination, and
scheduling of the work of the different trades.
Open Book
Contractual rights owners have to review and audit the
financial records of contractors performing cost-plus
contracts, may also include key team members.
Trade Builder
The party on the project responsible for performing and
overseeing construction for specific building systems on a project.
Copyright 2014 by The American Institute of Architects, California Council. All rights reserved.
17 INTEGRATED PROJECT DELIVERY - AN UPDATED WORKING DEFINITION
IPD STEERING COMMITEE
IPD STEERING COMMITEE
ACKNOWLEDGEMENTS
The following members of the design and construction industry served as
authors, editors and contributors of this document:
AIACC 2014 Executive Committee
Brian Dougherty, FAIA
President
Lee Salin, AIA
First Vice President/President-elect
Kim Anderson, Hon. AIACC
VP of CA Council of Component Executives
Bob DeGrasse, AIA
Secretary/Treasurer
Jana Itzen, AIA
VP of the Academy for Emerging Professionals
Greg Izor, AIA
VP of Regulatory Affairs
Bruce Monighan, AIA
Liaison to the California Architectural Foundation
Jason Silva, AIA
VP of Communications/Public Affairs
Don Rudy, AIA
VP of Legislative Affairs
Paul Welch Jr., Hon. AIA
Executive Vice President
IPD Steering Committee
Zigmund Rubel, AIA – Chair
Aditazz
Howard Ashcraft, Esq, Hon. AIACC
Hanson Bridgett LLP
Jim Bedrick, FAIA
AEC Process Engineering
J. Stuart Eckblad, AIA
UCSF Medical Center
Debra Gerod, FAIA
Gruen Associates
Don Rudy, AIA
Don Rudy AIA Architect
Mark Tiscornia, AIA
HGA
Oscia Wilson, AIA
Boiled Architecture
Nicki Dennis Stephens, Hon. AIACC,
LEED Green Assoc.
AIACC
THE AMERICAN INSTITUTE OF ARCHITECTS,
CALIFORNIA COUNCIL
1303 J Street, Suite 200,Sacramento, CA 95814
916/448-9082, 916/442-5346 fax
E-MAIL: [email protected]g, WEBSITE: www.ipd-ca.net